Construction on the A13 Sibiu-Făgăraș highway is progressing well, with the last metal segment of the arch bridge being installed. The Turkish contractor Makyol is working on a 164-meter arch bridge over the Ghirloțelul Sec stream, which is currently 72% complete. Two additional arch bridges are also under construction, with physical progress at 52% and 54.96% respectively. Overall, the four segments of the highway have physical completion rates ranging from 28.01% to 53.49%, with a total length of 68 km expected to be finished by 2028. The total contract value for these segments is 6.4 billion lei, funded through the Transport Program.