www.mediafax.ro/economic/181-de-km-noi-de-autostra

Cristian Pistol, the CEO of CNAIR, announced that three sections of the Transylvania Highway may open by year-end. Despite rain, construction continues on the A3. The physical progress of the works is 87.80% for the Topa Mică and Nădășelu viaducts, while the Nădășelu-Zimbor section is at 99.30%. The Suplacu de Barcău to Chiribiș segment is 95.39% complete. If all sections open, drivers will have 155 kilometers of highway available. However, a 40-kilometer unfinished stretch remains between Nușfalău and Poarta Sălajului, expected to be completed by 2031.