adevarul.ro/economie/instalatie-de-hidrogen-verde-
The green hydrogen production project by Tehnomir SRL in Bihor is under scrutiny after the Ministry of Energy found the facility non-functional despite payments exceeding 58 million lei. A monitoring visit revealed that the installation was not assembled or connected to the electrical grid, failing to meet technical indicators. The project, funded through PNRR, aimed for a production capacity of 9.06 MW H2 out but showed zero progress at the time of inspection. The report highlighted missing interconnections and incomplete installations, raising concerns about the project's viability and compliance with contractual obligations.