Alternativă la DN1: Lucrările au ajuns la 28% pe Valea Doftanei
The modernization of the DJ 102I county road between Valea Doftanei and Brădet is 28% complete, with nearly 2,000 drilled piles installed. The project aims to enhance a 25.63 km mountain route, providing an alternative to DN1 and improving road connections between Prahova and Brașov. Five bridges and 41 culverts are under construction, alongside significant infrastructure works. The road will feature an 8-meter wide platform with two lanes, modern accesses, and parking areas. The contract, valued at over 333 million lei, was awarded to Construcții Erbașu and is funded by the Ministry of Development. The project is expected to increase accessibility in the region.