A0 Nord: Loturile 3 și 4 ar urma să fie deschise săptămâna viitoare, dar pe lotul 1 CNAIR a refuzat o descărcare provizorie Autostrada A0: Loturile 3 și 4 vor fi deschise, lotul 1 mai așteaptă
The opening of Lot 4 of the A0 North Highway, built by UMB, is expected next week alongside Lot 3 by China Civil Engineering Corporation. Traffic on Lot 1 could have been partially opened, but CNAIR disagreed due to a pending expropriation lawsuit. Secretary of State Horațiu Cosma highlighted issues with initial planning of provisional exits and road nodes. The phased opening is crucial around Bucharest, where existing infrastructure is overloaded. The opening of Lots 3 and 4 would allow traffic on about 80% of the highway ring around Bucharest. A legal dispute over a building's expropriation may further delay the opening, risking another completed highway section to remain unused.