A fost montata ultima secțiune a podului peste Siret / Drumul Expres Brăila - Galați a ajuns la 97%
The Brăila–Galați Express Road project is nearing completion, with 97% physical progress reported. The last section of the metal deck for the bridge over the Siret River has been installed. The project, spanning nearly 11 kilometers, is expected to be finished this year. The bridge structure measures 1,790 meters and is a key component of the expressway. The construction is managed by UMB Spedition, with a budget of 449.42 million lei, funded through the Transport Program 2021–2027.