2,33 milioane de lei pentru reconfigurarea intersecției periculoase de acces spre Stupini. Vor fi amenajate și trotuare, precum și o trecere pentru pietoni • Administrație Biz Brasov
The traffic reconfiguration project in Stupini is nearing the final bureaucratic stage before the construction tender. The local council is set to approve the technical-economic indicators for the investment. The total cost is approximately 2.33 million lei, with a two-month construction timeline. The new roundabout will feature a dual-lane circular road, safety rings, and reflective islands. New sidewalks and a pedestrian crossing with safety measures will be added, along with modern LED street lighting. The project required the expropriation of 1,097 square meters of land, costing 143,160 lei.