FOTO: Lucrările pe sectorul Margina-Holdea al autostrăzii A1 avansează. Ce progrese au fost înregistrate pe unele secțiuni
Construction on the Margina-Holdea section of the A1 highway is progressing, with physical completion reaching about 70%. All 64 beams have been installed at the first overpass near Margina, while the second overpass is at 65% completion with 82 of 208 beams installed. The viaduct at kilometer 53+471 has all 24 beams in place, and work is ongoing on the slab reinforcement. In Holdea, 40 beams remain to be installed at one viaduct, while all beams are positioned at another. Future work will focus on completing slabs, waterproofing, road layers, and safety elements.