Se toarnă asfalt pe cel mai lung viaduct de autostradă din România. Când va fi deschis traficul

The construction of the longest viaduct in Romania, part of the A3 Transylvania Highway, has begun with the first layer of asphalt. Authorities aim to open traffic by the end of 2026. The project includes significant progress on various sections, with over 99% completion on 25 kilometers and 85% on another contract. The viaducts at Mihăiești and Nădășelu are also advancing, with essential stages like concrete pouring and asphalt laying underway. The overall goal is to enhance road connectivity between Cluj and Sălaj, with nearly 100 kilometers of new highway expected to open in 2026.